| International Correspondence Schools - 1903 - 652 стор.
...comprehended in this Agreement by and at the time or times hereinafter stated provided thatART. VII. Should the Contractor be obstructed or delayed in...work by the act, neglect, delay or default of the Oxvncr, or the> Architects, or of any other contractor employed by the Owner upon the work, or by any... | |
| 1904 - 1240 стор.
...under a written agreement between the parties, which, among other things, provided as follows: "Art. 7. Should the contractor be obstructed or delayed in...act, neglect, delay or default of the owner or the architect, or of any other contractor employed by the owner upon the work, or by any damage which may... | |
| New York (State). Courts, Francis Blaine Delehanty (Reporter), Austin B. Griffin (Reporter), Robert George Scherer (Reporter), Edward Jordan Dimock (Reporter), Joseph Albert Lawson (Reporter), Charles Cook Lester (Reporter), William Van Rensselaer Erving (Reporter), Louis J. Rezzemini (Reporter) - 1904 - 778 стор.
...furnish the detailed plans in time, as to which the contract provided that, if the contractor " be delayed in the prosecution or completion of his work...neglect, delay or default of the owner or the architects, * * * then the time herein fixed for the completion of the'work shall be extended for a period equivalent... | |
| Henry Robinson Towne - 1904 - 1146 стор.
...prosecution or completion of the work by the act, neglect, or default of the Owner, of the Architect, or of any other contractor employed by the Owner upon the work, w by any damage caused by fire, lightning, earthquake, cyclone or other casualty for which the Contractor... | |
| L. S. Le Vernois, Esten Kenneth Williams, Edward Betley Brown - 1905 - 670 стор.
...of his claim. But article 6 ie qualified and modified by article 7, which reads aw follows : — " Should the contractor be obstructed or delayed in...act, neglect, delay, or default of the owner, or the architect, or of any other contractor employed by the owner upon the work, or by any damage which may... | |
| Illinois. Court of Claims - 1905 - 420 стор.
...day of April, AD 1899, and time was made of the essence of the contract. Article VII provided that, "Should the contractor be obstructed or delayed in...work by the act, neglect, delay or default of the Commissioners, or the Architects, or of any other contractor employed by the Commissioners upon the... | |
| Edward Betley Brown, L. S. Le Vernois, Esten Kenneth Williams - 1905 - 622 стор.
...amount of his claim. But article 6 is qualified and modified by article 7, which reads as follows:—" Should the contractor be obstructed or delayed in...completion of his work by the act, neglect, delay, br default of the owner, or the architect, or of any other contractor employed by the owner upon the... | |
| 1907 - 806 стор.
...precluded from defending on that ground by virtue of the contract provision following, viz. : "That should the contractor be obstructed or delayed In...prosecution or completion of his work by the act, neglect, default or delay of the owner or architect, or of any other contractor, employed by the owner, or Robinson... | |
| Wilbur Jay Watson - 1908 - 92 стор.
...prosecution or completion of the work by the act, neglect or default of the Owner, of the Engineer, or of any other Contractor employed by the Owner upon the work, or by damage caused by fire or other casualty for which the Contractor is not responsible, or by general... | |
| 1909 - 1316 стор.
..."Should the contractor be delayed In the prosecution or completion of the work l,y the art, neglect or default of the owner or the architects or of any...employed by the owner upon the work or by any damage caused by fire, lightning, earthquake, cyclone or other casualty for which the contractor is not responsible... | |
| |