...prosecution or completion of the work by the act, neglect or default of the Owner , of the Architect , or of any other contractor employed by the Owner upon the work, or by any damage caused by Ore, lightning, earthquake, cyclone or other casualty for which the Contractor not responsible,... | |
| William A. Radford, Alfred Sidney Johnson - 1909 - 446 стор.
...prosecution or completion of the work by the act, neglect, or default of the Owner , of the Architect , or of any other contractor employed by the Owner upon the work, or by any damage caused by fire or other casualty for which the Contractor not responsible, or by combined action of... | |
| 1909 - 1360 стор.
...prosecution or completion of the work by the act, neglect or default of the owner, of the architect, or of any other contractor employed by the owner, upon the work, or by any damage caused by fire, lightning, earthquake, cyclone or other casualty, for which the contractor is not responsible,... | |
| Charles Evan Fowler - 1909 - 180 стор.
...due or to become due the Contractor from the Owner on account of this or any other contract. Seventh. Should the Contractor be obstructed or delayed in the prosecution or completion of the work by the neglect, delay or default of any other contractor; or by an alteration which may be... | |
| Massachusetts. Supreme Judicial Court - 1909 - 782 стор.
...every day prior to said September 1st, 1902, that the said work is so fully completed. " Art. VII. Should the Contractor be obstructed or delayed in the prosecution or completion of bis work by the act, neglect, delay or default of the Owner, or the Architect, or of any other Contractor... | |
| New York (State). Supreme Court. Appellate Division - 1910 - 1092 стор.
...delayed in the prosecution or completion of the work by the act, neglect or default of the owner, of the architects, or of any other contractor employed by the owner upon the work, or by any damage caused by fire, lightning, earthquake, cyclone or other casualty for which the contractor is not responsible,... | |
| John Joseph Cosgrove - 1910 - 230 стор.
...delayed in the prosecution or completion of the work by the act, neglect or default of the Owner, of the Architects, or of any other contractor employed by the Owner upon the work, or by any damage caused by fire or other casualty for which the Contractor not responsible, or by combined action of... | |
| 1910 - 472 стор.
...prosecution or completion of the work by the act, neglect or default of the Owner , of the Architect, , or of any other contractor employed by the Owner upon the work, or by any damage caused by tiro, lightning, earthquake, cyclone or other casualty for which the Contractor — not responsible,... | |
| L. S. Le Vernois, Esten Kenneth Williams - 1911 - 770 стор.
...not a penalty: 1 Hudson on Building Contracts, p. 581. Article VII. of the contract is as follows : " Should the contractor be obstructed or delayed in the prosecution or completion of the works by reason of the act of neglect, delay, or default of the owner or of the architect or of... | |
| Washington (State). Supreme Court, Arthur Remington, Solon Dickerson Williams - 1912 - 840 стор.
...binding, and each of the parties hereto shall pay one-half of the expense of such reference." "(7) Should the contractor be obstructed or delayed in...act, neglect, delay or default of the owner, or the architect, or of any other contractor employed by the owner upon the work, or by any damage which may... | |
| |