| Harris Denison Grant - 1922 - 272 стор.
...the causes aforesaid, which extended period shall be determined and fixed by the Architect ; but no allowance shall be made unless a claim therefor is...forty-eight hours of the occurrence of such delay: Sections. — The Owner. . agree. . to provide all labor and materials essential to the conduct of... | |
| Samuel Williston, Clarence Martin Lewis - 1922 - 752 стор.
...extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefor is presented in writing to the General Contractors within twentyfour hours after the occurrence of such delay. The General Contractors... | |
| Iowa. Supreme Court - 1922 - 1512 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the architects, but no such allowance shall be made unless a claim therefor is presented in writing to the architects within 48 hours of the occurrence of such delay. * * * "Article XXI. Should the owner on... | |
| 1924 - 1054 стор.
...of time for completing the building equivalent to any delay caused by the act of the owner, but that "no such allowance shall be made unless a claim therefor is presented in writing to the architect and consulting architects within 24 hours of the occurrence of such delay." No such claim was presented... | |
| William Maurice Affelder - 1924 - 408 стор.
...time lost by reason of any of the causes aforesaid. This extension shall be determined and fixed by Architect, but no such allowance shall be made unless a claim therefor is presented in writing to Contractor within fortyeight (48) hours of the occurrence of delay, and such claim approved :n writing... | |
| 1916 - 1096 стор.
...all the causes aforesaid, which extended j>eriod shall be determined and fixed by the architects ; but no such allowance shall be made unless a claim therefor is presented in writing to the architects within forty eight hours of the occurrence of such delay. "Art. VIII. The owners agree to... | |
| 1922 - 498 стор.
...extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid ; but no such allowance shall be made unless a claim...therefor is presented in writing to the Architect within twentyfour hours of the occurrence of such delay. The duration of such extension shall be certified... | |
| 1928 - 1232 стор.
...extended for a period equal to the time lost by reason of any such cause. But it also provides that no such allowance shall be made unless a claim therefor...writing to the architect within forty-eight hours after the occurrence of such 'delay. Thus it will be seen that the contract expressly provides for... | |
| United States. Board of Tax Appeals - 1928 - 1582 стор.
...shall be extended for a period equivalent to the time lost by reason of any or all causes aforesaid ; but no such allowance shall be made unless a claim therefor is presented to the Architects within twenty-four hours of the occurrence of such delay. The duration of such extension... | |
| American Institute of Architects - 1906 - 524 стор.
...all of the causes aforesaid, which extended period shall be determined and fixed by the Architects; but no such allowance shall be made unless a claim therefor is presented in writing to the Architects within forty-eight hours of the occurrence of such delay." The Committee, after expressing... | |
| |