| Connecticut. Office of the Attorney General - 1909 - 304 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the Architect; but no such allowance shall be made unless a claim therefor is presented in writing to the Architect within forty-eight hours of the occurrence of such delay." Art. VII does not deal with compensation... | |
| 1909 - 1360 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no such allowance shall be made unless a claim therefor Is presented in writing to the architect within forty-eight hours of the occurrence of such delay." It is obvious that the provision... | |
| John Joseph Cosgrove - 1910 - 226 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the Architects ; but no such allowance shall be made unless a claim...therefor is presented in writing to the Architects within forty-eight hours of the occurrence of such delay. ART. VIII. The Owner agree to provide all labor... | |
| 1910 - 472 стор.
...or all the causes aforesaid, which exteiidvd period shall be determined and fixed by the Architect ; but no such allowance shall be made unless a claim therefor is presented in writing to the Architect within torty-eight hours of the occurrence of such delay. ART. VIII. TheOwner agree to provide... | |
| Washington (State). Supreme Court, Arthur Remington, Solon Dickerson Williams - 1912 - 840 стор.
...happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the employees through no default of the contractor, then the time...unless a claim therefor is presented in writing to the architect within twenty-four hours of the occurrence of such delay. The duration of such extension... | |
| 1912 - 1038 стор.
...abandonment of the work by the employees of the contractors tb rough no default of the contractors, then the time herein fixed for the completion of the...unless a claim therefor is presented in writing to the owner within twenty-four hours of the occurrence of such delay. Should the parties be unable to agree... | |
| 1912 - 1276 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the architects; but no such allowance shall be made unless a claim...therefor is presented In writing to the architects within 48 hours of the occurrence of such delay." Because of this provision, and of the many causes for delay... | |
| 1912 - 478 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the Architect : but no such allowance shall be made unless a claim therefor is presented in writing to the Architect within forty-eight hours of the occurrence of such delay. AI«T. V111. The Owner agree to... | |
| Richard Shelton Kirby - 1913 - 174 стор.
...which extended period shall be determined and fixed by the Architect: but no such allowance of time shall be made unless a claim therefor is presented in writing to the Architect within forty-eight hours of the occurrence of the delay." From standard building contract... | |
| William A. Radford - 1913 - 912 стор.
...amount of such compensation shall be determined and awarded by the Architect (subject to arbitration); but no such allowance shall be made unless a claim therefor is made in writing or by telegraph to the Architect within forty-eight hours of the occurrence of such... | |
| |