" Contractor , then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all... "
Stair Building ; Ornamental Ironwork ; Roofing ; Sheet-metal Work ; Building ... - Сторінка 84
автори: International Correspondence Schools - 1903 - 627 стор.
Повний перегляд - Докладніше про цю книгу

Reports of Cases at Law and in Chancery Argued and Determined in ..., Том 255

Illinois. Supreme Court - 1913 - 712 стор.
...or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no such allowance shall be made unless a claim therefor is presented, in writing, to the architect within forty-eight hours of the occurrence of such delay." The plaintiff then offered in...
Повний перегляд - Докладніше про цю книгу

Cases Decided in the Court of Claims of the United States, Том 66

United States. Court of Claims - 1929 - 868 стор.
...allowed. " which extended period shall be determined and fixed by the Director [of the Veterans' Bureau] ; but no such allowance shall be made unless a claim therefor is presented in writing to the Director within forty-eight hours of the occurrence of such delay." and that $25.00 per day was to...
Повний перегляд - Докладніше про цю книгу

Cases Decided in the United States Court of Claims ... with Report ..., Том 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 стор.
...equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless a claim therefor is presented in writing to the Contractor within seven (7) days of the occurrence of such delay. The subcontractor shall not have,...
Повний перегляд - Докладніше про цю книгу

The Pacific Reporter, Том 68

1902 - 1166 стор.
...to be done shall be extended for a period equivalent to the delay so caused, but no such extension shall be made unless a claim therefor Is presented In writing to the owner within 24 hours after the delay, — the duration of the extension to be certified by the owner;...
Повний перегляд - Докладніше про цю книгу

The Southwestern Reporter, Том 147

1912 - 1356 стор.
...extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall be made, unless a claim therefor Is presented In writing to the architect within 48 hours after the occurrence of such delay. Thus it will be seen that the contract...
Повний перегляд - Докладніше про цю книгу

Arkansas Reports: Cases Determined in the Supreme Court of the ..., Том 104

Arkansas. Supreme Court - 1913 - 694 стор.
...extended for a period equal to the time lost by reason of any such cause. But it also provides that no such allowance shall be made unless a claim therefor is presented in writing to the architect within forty-eight hours after the occurrence of such delay. Thus it will be seen that the...
Повний перегляд - Докладніше про цю книгу

Official Report ... Annual Convention, Том 8,Частина 1894

National Association of Builders of the United States of America - 1894 - 274 стор.
...be for the protection of the contractor. For the protection of the architect, we put this in : — But no such allowance shall be made unless a claim...twenty-four hours of the occurrence of such delay. four hours to make good your claim. Now the duration or existence of such things, if they are not satisfactory...
Повний перегляд - Докладніше про цю книгу

Electric Lighting Specifications for the Use of Engineers and Architects

Earle Abbott Merrill - 1896 - 222 стор.
...completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid; but no such allowance shall...therefor is presented in writing to the Architects within twenty •= four hours of the occurrence of such delay. The duration of such extension shall be certified...
Повний перегляд - Докладніше про цю книгу

Transactions of the American Society of Mechanical Engineers, Том 22

American Society of Mechanical Engineers - 1901 - 1776 стор.
...completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid ; but no such allowance shall...hours of the occurrence of such delay. The duration of inch extension shall be certified to by the Architects, but appeal from their decision may be made...
Повний перегляд - Докладніше про цю книгу

Reports of Cases Argued and Determined in the Supreme Court of the ..., Том 112

Wisconsin. Supreme Court, Abram Daniel Smith, Philip Loring Spooner, Obadiah Milton Conover, Frederic King Conover, Frederick William Arthur, Frederick C. Seibold - 1902 - 780 стор.
...for the completion of the building should be extended for a period equivalent to the time so lost; " but no such allowance shall be made unless a claim therefor is presented in writing to the architect within twenty-four hours of the occurrence of such delay. The duration of such extension...