Сторінка 581 - Material which is to be used without annealing or further treatment is to be tested in the condition in which it comes from the rolls. When material is to be annealed or otherwise treated before use, the specimen representing such material is to be similarly treated before testing.
Сторінка 26 - The PRESIDENT. The next business in order is the report of the Committee on Credentials.
Сторінка 41 - Owner shall be at liberty, after three days written notice to the Contractor , to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the Contractor under...
Сторінка 423 - It shall not be lawful for any person, other than those connected with or employed upon the railroad, to walk along the track or tracks of any railroad, except where the same shall 'be laid along public roads or streets.
Сторінка 41 - ... and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the...
Сторінка 407 - Until such fences and cattle-guards shall be duly made, the corporation and its agents shall be liable for all damages which shall be done by their agents or engines to cattle, horses, or other animals thereon ; and after such fences and guards shall be duly made and maintained, the corporation shall not be liable for any such damages, unless negligently or willfully done...
Сторінка 42 - ... of the Contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid ; but no such allowance shall be made unless a claim therefor is presented in writing to the Architect within twentyfour hours of the occurrence of such delay.
Сторінка 410 - That every railroad corporation, shall, within six months after any part of its line is open for use, erect and thereafter maintain fences on both sides of its road or so much thereof as is open for use, suitable and sufficient to prevent cattle, horses, sheep, hogs or other stock from getting on such railroad, except at the crossings of public roads and highways, and within such portion of cities and incorporated towns and villages as are or may be hereafter laid out and platted into lots and blocks...
Сторінка 41 - ... the expense incurred by the Owner in finishing the work, such excess shall be paid by the Owner to the Contractor ; but if such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner . The expense incurred by the Owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the Architect, whose certificate thereof shall be conclusive upon the parties.
Сторінка 41 - The Architects shall furnish to the Contractor such further drawings or explanations as may be necessary to detail and illustrate the work to be done, and the Contractor shall conform to the same as part of this contract so far as they may be consistent with the original drawings and specifications referred to and identified, as provided in Art.