| Illinois. Supreme Court - 1913 - 712 стор.
...responsible, or by general strikes or lockouts caused by acts of employees, then the time herein fixed for the completion of the work shall be extended for...period equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect;... | |
| Illinois. Supreme Court - 1908 - 710 стор.
...abandonment of the work by employees through no fault of the contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time Iqst by reason of any or all of the causes aforesaid." Article 8 stipulates that the owner shall pay... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 908 стор.
...Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless... | |
| British Columbia - 1913 - 696 стор.
...other unavoidable causes, then the time herein fixed for the doing or completion of any such works shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid. The period of such extension shall, if the City and Railway Company... | |
| 1913 - 1174 стор.
...responsible, or by general strikes or lockouts caused by nets of employes, then the time herein fixed for the completion of the work shall be extended for...period equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect;... | |
| 1905 - 1156 стор.
...the act, neglect, delay, or default of the owner or the architects, » • • then the time fixed for the completion of the work shall be extended for...period equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefor is presented... | |
| 1914 - 1134 стор.
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless... | |
| 1902 - 1270 стор.
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves... | |
| 1912 - 1356 стор.
...completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall... | |
| 1915 - 1242 стор.
...resulting from default or collusion on the part of the contractor, then the time herein fixed for (he completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid. *• * * " The contractor did employ union labor, as he had agreed... | |
| |