" ... in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished... "
Electric Lighting Specifications for the Use of Engineers and Architects - Сторінка 208
автори: Earle Abbott Merrill - 1896 - 213 стор.
Повний перегляд - Докладніше про цю книгу

Michigan Reports: Cases Decided in the Supreme Court of Michigan, Том 200

Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1919 - 806 стор.
...other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor,...the unpaid balance of the amount to be paid under the contract shall exceed the expense incurred by the owners in finishing the work, such excess shall...
Повний перегляд - Докладніше про цю книгу

Michigan Reports: Cases Decided in the Supreme Court of Michigan, Том 187

Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1916 - 804 стор.
...employment of the contractor the contractor shall not be entitled to receive any further payment under the contract until the said work shall be wholly finished,...the unpaid balance of the amount to be paid under the contract shall exceed the expense incurred by the owner in finishing the work, such expense shall...
Повний перегляд - Докладніше про цю книгу

The Federal Reporter: Cases Argued and Determined in ..., Томи 87 – 88

1898 - 2046 стор.
...should not be entitled to receive any further payment under said contract until the said work should be wholly finished, at which time, if the unpaid balance of the amount to be paid under said contract should exceed the expense incurred by plaintiff in finishing the work, such excess should...
Повний перегляд - Докладніше про цю книгу

The Federal Reporter, Том 243

1917 - 1038 стор.
...contractor, who shall pay to the party of the first part the excess thereof, if any, over and above the unpaid balance of the amount to be paid under this contract ; and the contractor shall have no claim or demand to such unpaid balance, or by reason of the nonpayment...
Повний перегляд - Докладніше про цю книгу

The Federal Reporter: Cases Argued and Determined ..., Томи 243 – 244

1917 - 2042 стор.
...contractor, who shall pay to the party of the first part the excess thereof, if any, over and above the unpaid balance of the amount to be paid under this contract ; and the contractor shall have no claim or demand to such unpaid balance, or by reason of the nonpayment...
Повний перегляд - Докладніше про цю книгу

The Pacific Reporter, Том 119

1912 - 1170 стор.
...provide the materials therefor ; and In case of such discontinuance of the employment of the con. tractor he shall not be entitled to receive any further payment...finished, at which time, if the unpaid balance of the amouiit to be paid under this contract shall exceed the expense Incurred by the owner In finishing...
Повний перегляд - Докладніше про цю книгу

The Pacific Reporter, Том 133

1913 - 1236 стор.
...contractor's employment. To provide for that contingency the paragraph declares that, "in case of such discontinuance of the employment of the contractor,...receive any further payment under this contract,'' uutll the work shall have been wholly finished by the owiier. It will be seen that the right to receive...
Повний перегляд - Докладніше про цю книгу

The Pacific Reporter, Том 140

1914 - 1230 стор.
...the materials therefor; and in ease of such discontinuance of the employment of the contractors they shall not be entitled to receive any further payment under this contract until such work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under...
Повний перегляд - Докладніше про цю книгу

The Atlantic Reporter, Том 70

1908 - 1148 стор.
...person or persons to finish the work, and to provide the materials tlierefor, and, In case of such discontinuance of the employment of the contractor,...finished, at which time, if the unpaid balance of the whole amount to be paid under this contract shall exceed the expense Incurred by the owner in finishing...
Повний перегляд - Докладніше про цю книгу

Atlantic Reporter, Том 65

1907 - 1150 стор.
...said George Jewell, he shall not be entitled to any further payments under this contract until the work shall be wholly finished, at which time, if the...amount to be paid under this contract shall exceed the expenses incurred by the said Henry Smith & Sons In finishing the work, such excess shall be paid to...
Повний перегляд - Докладніше про цю книгу